Steel Authority of India ,CAST STUDY solution
The following table shows the jobs of a project with their duration in days
a) Draw the network diagram.
(b) Compute the earliest event event time
(c) Determine the critical path duration
7 . Write short notes on any fiue of the following :
(a) VED Analysis
(b) Consumer's risk
(c) Learning Curve
(d) Standardization and Codification
(e) Delphi Technique (0 Bill of Materials